MS Project - Early Dates vs Late Dates

I
Ian Thomson 👤 Member for 22 years 10 months
R
Robyn Brown 👤 Member for 21 years 7 months

Hi,



The early late dates Graph for M/S can be produced from within MS Project then exported automaticccaly to excel to provide the S Curve using VBA code.





Regards

P
Paul Harris 👤 Member for 25 years 3 months

It is possible to get an S-Curve from MSP but it is not the best presentation. Select the tasks a top window Gantt chart, show the resource Graph on the bottom window, right click & select the Cumulative Work, Select Bar styles… and select line for all and/or selected tasks.



Most people I know export the data to Excel to create S-curves using one of the export functions. I like the Analyze timescale data in Excel function found on the Analysis toolbar. They produce the S-Curves from Excel.



To make a late curve I make sure I have a closed network and I usually then make all the activities ASAP to create the Late curve. Hopefully someone has a better method than this but I have not found any other method of producing a late curve.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers & Consulting

www.eh.com.au

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts