MS Project - Early Dates vs Late Dates
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Hi,
The early late dates Graph for M/S can be produced from within MS Project then exported automaticccaly to excel to provide the S Curve using VBA code.
Regards
It is possible to get an S-Curve from MSP but it is not the best presentation. Select the tasks a top window Gantt chart, show the resource Graph on the bottom window, right click & select the Cumulative Work, Select Bar styles… and select line for all and/or selected tasks.
Most people I know export the data to Excel to create S-curves using one of the export functions. I like the Analyze timescale data in Excel function found on the Analysis toolbar. They produce the S-Curves from Excel.
To make a late curve I make sure I have a closed network and I usually then make all the activities ASAP to create the Late curve. Hopefully someone has a better method than this but I have not found any other method of producing a late curve.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia