I view the situation wherein the old program was, is and will be considered as the approved contractual construction program. I took notice of the statement "we force the sub-contractors..." that I may construe as exerting undue influence". In this case the recovery program is not contractually binding to all hence the recovery program has no relation with the original program.
If Ive understood you correctly, you program has gone into a major exception situation, from which a recovery plan was produced and the outstanding work rescheduled. With the organisation I work for, if that happens the work is carried out to the recovery plan as the original plan has no relevance now.
The work that has been completed is out of the equation and resources are concentrated on the work to be carried out under the recovery plan. Any percentages of completion are measured against the work in the recovery plan alone.
I suppose if you had to, you could do something like this:
1) Measure the percentage of completion under the original plan for the work carried out before the exception situation.
2) Determine which items of work have been carried out under the recovery plan and what items they equate to under the original plan.
3) Work out the percentage completion under the recovery plan.
4) Work out the additional percentage completion under the original plan and adjust the percentage calculated in step 1) accordingly.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hello,
I view the situation wherein the old program was, is and will be considered as the approved contractual construction program. I took notice of the statement "we force the sub-contractors..." that I may construe as exerting undue influence". In this case the recovery program is not contractually binding to all hence the recovery program has no relation with the original program.
Hi there,
If Ive understood you correctly, you program has gone into a major exception situation, from which a recovery plan was produced and the outstanding work rescheduled. With the organisation I work for, if that happens the work is carried out to the recovery plan as the original plan has no relevance now.
The work that has been completed is out of the equation and resources are concentrated on the work to be carried out under the recovery plan. Any percentages of completion are measured against the work in the recovery plan alone.
I suppose if you had to, you could do something like this:
1) Measure the percentage of completion under the original plan for the work carried out before the exception situation.
2) Determine which items of work have been carried out under the recovery plan and what items they equate to under the original plan.
3) Work out the percentage completion under the recovery plan.
4) Work out the additional percentage completion under the original plan and adjust the percentage calculated in step 1) accordingly.
Hope that this is some use.
Chris Oggham