Task Levelling when Tasks Completed
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Thanks very much for the tip - Ill give it a go.
Regards,
Steve
Steve
Microsoft Project does not have a strong leveling engine.
The only method I know to stop this type of messing around where MSP levels completed work and ignores Actual Dates, which is not too clever and very frustrating, is to display the Resource Usage Sheet in the bottom pane and enter the actual hours against the completed work. This also changes the Resource Contour to “Contoured”. It may then level as you hope.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Book Publishers, Training & Consulting
www.eh.com.au