Task Levelling when Tasks Completed

P
Paul Harris 👤 Member for 25 years 1 month

Steve



Microsoft Project does not have a strong leveling engine.



The only method I know to stop this type of messing around where MSP levels completed work and ignores Actual Dates, which is not too clever and very frustrating, is to display the Resource Usage Sheet in the bottom pane and enter the actual hours against the completed work. This also changes the Resource Contour to “Contoured”. It may then level as you hope.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Book Publishers, Training & Consulting

www.eh.com.au