Thanks



I’ve had a play around with it and as a workaround have added it as a material cost and loaded the number of units in the resource allocation to equal the number of days that task requires.



If anyone can think of a smarter way of doing it, please let me know.



Dan

W
Will Russell 👤 Member for 23 years 2 months

Using the Cost tab in the Resource Information box you can put in specific costs for certain periods of time as you wanted.