Ive had a play around with it and as a workaround have added it as a material cost and loaded the number of units in the resource allocation to equal the number of days that task requires.
If anyone can think of a smarter way of doing it, please let me know.
Dan
Using the Cost tab in the Resource Information box you can put in specific costs for certain periods of time as you wanted.
Will