I think it is a good thing when threads cross over disciplines. There are factors in the QS realm that does have a direct bearing on project planning.
Ken Sadler gives excellent advice in this forum on money and contract issues - paricularly on the issue of defined and non-defined provisional sums - and he is not a planner.
Not only the wrong forum but not a planning issue!
As planners we dont give a monkies if the blocks are green yellow or gold. We dont care if they cost twice or three times the price, we are only bothered if they take longer to lay or longer to procure!
Please guys leave the money to the bean counters who are paid far more than us!
For what its worth I consider that drawings nearly allways take priority over bills of quantities.
You will need to check your Contract document regarding the Priority of Documents. If your contract is under FIDIC, then as per clause 1.5 the priority is in the following sequence:
a) The Contract Agreement
b) The Letter of Acceptance
c) the Letter of Tender
d) the Particular Conditions
e) General Conditions
f) specifications
g) drawings
h) Schedules
The same clause also mentions that "if an ambiguity if discrepency is found in teh documents , the Engineer shall issue and necessary clarification of instruction."
And if you go the clause 1.1.1.7 the definition of
"Schedule: means the documents entitled schedules, completed by the Contractor and submitted with the Letter of Tender as included in the Contract. Such document may include the Bill of Quantities, data, lists, and schedules of rates and/ or prices."
This thread is in the wrong forum category - please try to place your threads correctly.
Meanwhile if there is a discrepancy in the contract documants you normally have to notify the Architect / Engineer / CA for an instruction as to what is required.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hi Andrew
I think it is a good thing when threads cross over disciplines. There are factors in the QS realm that does have a direct bearing on project planning.
Ken Sadler gives excellent advice in this forum on money and contract issues - paricularly on the issue of defined and non-defined provisional sums - and he is not a planner.
Best regards
Mike Testro
Not only the wrong forum but not a planning issue!
As planners we dont give a monkies if the blocks are green yellow or gold. We dont care if they cost twice or three times the price, we are only bothered if they take longer to lay or longer to procure!
Please guys leave the money to the bean counters who are paid far more than us!
For what its worth I consider that drawings nearly allways take priority over bills of quantities.
Dear Balachandran,
You will need to check your Contract document regarding the Priority of Documents. If your contract is under FIDIC, then as per clause 1.5 the priority is in the following sequence:
a) The Contract Agreement
b) The Letter of Acceptance
c) the Letter of Tender
d) the Particular Conditions
e) General Conditions
f) specifications
g) drawings
h) Schedules
The same clause also mentions that "if an ambiguity if discrepency is found in teh documents , the Engineer shall issue and necessary clarification of instruction."
And if you go the clause 1.1.1.7 the definition of
"Schedule: means the documents entitled schedules, completed by the Contractor and submitted with the Letter of Tender as included in the Contract. Such document may include the Bill of Quantities, data, lists, and schedules of rates and/ or prices."
Hi Balachrandan
This thread is in the wrong forum category - please try to place your threads correctly.
Meanwhile if there is a discrepancy in the contract documants you normally have to notify the Architect / Engineer / CA for an instruction as to what is required.
Best regards
Mike Testro