I beg your pardon Miss, but I cannot agree with you saying P3 will soon be off the market; just ask any Primavera Autorized Parner the question how difficult they have persuading customers switching from P3 to PM6.
In the whole world, P3 is regarded as much more fitted for standalone planners working in a no network environnement, such as public works, oil and gas work sites in Africa.
In France too, the market share is much more toward P3 than its successors.
What is true is: P3 has an old-looking user interface, it takes MS Excel or Lotus 123 to enter large amounts of tasks and data, ... PM5/6 is much more modern looking
Because P3 users do not want to switch and keep purchasing P3 boxes, Primavera Corp dramatically changed P3 prices last year, going up from 3000 to 5000 US$ a piece.
As far as I am concerned, I like both products, I reckon PM6 is easier to work fast than P3, but should I take one on remote island, it would be P3
Long live Primavera scheduling tools, whatever they are
basically, you need to be a builder or a fabricator (knowing the activities), then a bean counter or a quantity surveyor(for cost cutting and value engineering), then a cost engineer or a contracts administrator for contractual matters, btw, you need to understand deeply the procurement process, because the long-lead items have a very large impact with regards to schedule, then i suggest you take a training from a qualified trainor to understand how the software works
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Carmen,
I beg your pardon Miss, but I cannot agree with you saying P3 will soon be off the market; just ask any Primavera Autorized Parner the question how difficult they have persuading customers switching from P3 to PM6.
In the whole world, P3 is regarded as much more fitted for standalone planners working in a no network environnement, such as public works, oil and gas work sites in Africa.
In France too, the market share is much more toward P3 than its successors.
What is true is: P3 has an old-looking user interface, it takes MS Excel or Lotus 123 to enter large amounts of tasks and data, ... PM5/6 is much more modern looking
Because P3 users do not want to switch and keep purchasing P3 boxes, Primavera Corp dramatically changed P3 prices last year, going up from 3000 to 5000 US$ a piece.
As far as I am concerned, I like both products, I reckon PM6 is easier to work fast than P3, but should I take one on remote island, it would be P3
Long live Primavera scheduling tools, whatever they are
Alexandre
hi ms carmen arape
thanks a lot!
bon
Urbicio,
do not loose your time with P3. I will be OFF the market very soon. Instead, learn P5 or P6.
Cheers,
basically, you need to be a builder or a fabricator (knowing the activities), then a bean counter or a quantity surveyor(for cost cutting and value engineering), then a cost engineer or a contracts administrator for contractual matters, btw, you need to understand deeply the procurement process, because the long-lead items have a very large impact with regards to schedule, then i suggest you take a training from a qualified trainor to understand how the software works