Planning Planet Planning Norms
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Charlie
Whenever possible I try and have only one start and one finish. This is not always possible as you say due to (my) time constraints, merging programmes together etc.
When I run the schedule I always try and remove some of the open ends. Having imparted this knowledge to other planners and suggested that they tie up the project, the danger is that they will add everything to the start project milestone and again to the end project milestone.
Some activities are not really linkable in a logical way - meetings for one. But linking everything to the start or finish is not a good idea.
In principle I agree with what you say, in practice, hmmm. Rain check.
Cheers
Nige