using weight

J
Jafar Zarei 👤 Member for 22 years 11 months
M
MK TSE 👤 Member for 24 years 3 months

Use a custom field to store the value of weighting. Copy the required columns from Project to X-L, calculate the progress according to the weighting factor. Copy and paste the progress back to Project.



(btw, if formula is allowed in Project, no X-L required)