Level of effort activity

Good morning all,

please,could some one to explain me why:

i have created a LOEF activity for rented non labor resource for a certain number of activities.

i have created a base line for my plan.During the progress my plan shown a certain delay ,there for the gant bar of activities and baseline are no longer superimposed,but instead to see the bar of level of effort linked to the actual activities ,i see the bar of level of effort is linked to the last bar of the baseline.what is wrong in the begining.

A
amar iadaden 👤 Member for 7 years 11 months

Thanks Kelly for your reply

I tried to move up and down the level of effort bar ,but there is no change.The relationship FF remains attached to baseline bar.

A
amar iadaden 👤 Member for 7 years 11 months

Good morning Kelly,

as my question is not clear , i rephrase my question.

during the progress, the relationship Finish to finish  of the level of effort activity is with the baseline bar of the last activity instead of the last remaining activity bar.

i hope it is clear now.

D
david kelly 👤 Member for 10 years 3 months

Yes, it is clear now.

It is the position of the bar definitions in the dialogue that controls them, which determines the bars that the relationship lines join. You move the bar definitions up and down in the list to change.

A
amar iadaden 👤 Member for 7 years 11 months

Good morning Kelly,

as my question is not clear , i rephrase my question.

during the progress, the relationship Finish to finish  of the level of effort activity is with the baseline bar of the last activity instead of the last remaining activity bar.

i hope it is clear now.

A
amar iadaden 👤 Member for 7 years 11 months

Good morning Kelly,

as my question is not clear , i rephrase my question.

during the progress, the relationship Finish to finish  of the level of effort activity is with the baseline bar of the last activity instead of the last remaining activity bar.

i hope it is clear now.

A
amar iadaden 👤 Member for 7 years 11 months

Good morning Kelly,

as my question is not clear , i rephrase my question.

during the progress, the relationship Finish to finish  of the level of effort activity is with the baseline bar of the last activity instead of the last remaining activity bar.

i hope it is clear now.

D
david kelly 👤 Member for 10 years 3 months

Not completely clear what you are asking, Amar.

The relationship lines, showing in the bar chart, are drawn between the bars listed first in the Bars dialogue. By default, Primavera lists the baseline bars BEFORE the remaining bars. To change this, you move the bars up and down in the bars dialogue. Does that help?

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts