Particular Resource assignment automatically in Primavera among the group of Resources

Hi

Need your support here.

This is related to Manufacturing planning works.

Activity A - Machining operation - 15 days

Activity B - Machining operation - 10 days

Activity C - MAchining operation - 20 days

Activity D - Machining operation - 25 days

Activity E - Machining operation - 5 days

Activity F - Machining operation - 5 days.

All activites were independent. We are having two resources say LATHE 1 and LATHE 2. Is it possible in Primavera , assigning the resource for the above activities ( either LATHE 1 or LATHE 2 ) will be done automatically depends on the resource loading/activity operation to get better result. (Shortest Project Duration).

 

Thanks in advance

Ram

Featured Partner

Top Posters

Jeamiell Ostrovsky
2 posts
Hamzah Ahmed
0 posts
Quinton van Eeden
3 posts
Sunchana Johnston
12 posts
Akram Hammam Mohamed
17 posts
Sagar Raut
14 posts
Patricio_aoa
0 posts
James Williams
75 posts
Philip Assou-Dodji
1 posts
jeoffrey reyes
15 posts