Particular Resource assignment automatically in Primavera among the group of Resources

Hi

Need your support here.

This is related to Manufacturing planning works.

Activity A - Machining operation - 15 days

Activity B - Machining operation - 10 days

Activity C - MAchining operation - 20 days

Activity D - Machining operation - 25 days

Activity E - Machining operation - 5 days

Activity F - Machining operation - 5 days.

All activites were independent. We are having two resources say LATHE 1 and LATHE 2. Is it possible in Primavera , assigning the resource for the above activities ( either LATHE 1 or LATHE 2 ) will be done automatically depends on the resource loading/activity operation to get better result. (Shortest Project Duration).

 

Thanks in advance

Ram

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts