How to determine Total Float Calculation for Critcal Path

K
KT G23 👤 Member for 10 years 10 months

Hi Guys

I am reviewing a contractor P6 programme that has 0 Total Float as it is due to finish before the 'Must Finish By' date. It is therefore showing no Critical Path when scheduled using the Default setting 'Total Float less than 0d'. Can anyone advise what would be best way to determine a Total Float value for the Critical Path calculation? I've tried the longest path setting instead but it's not valid as activities are constrained.

Any advice would be much appreciated.

Thanks

J
Jithin Kambhikanam 👤 Member for 15 years 2 months

Go to Project - Click on the Project - In the bottom go to settings

In settings go to Define critical Activities and mention the Total Float less than or equal to = which which would be considered as Critical

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts