How to determine Total Float Calculation for Critcal Path

K
KT G23 👤 Member for 11 years

Hi Guys

I am reviewing a contractor P6 programme that has 0 Total Float as it is due to finish before the 'Must Finish By' date. It is therefore showing no Critical Path when scheduled using the Default setting 'Total Float less than 0d'. Can anyone advise what would be best way to determine a Total Float value for the Critical Path calculation? I've tried the longest path setting instead but it's not valid as activities are constrained.

Any advice would be much appreciated.

Thanks

J
Jithin Kambhikanam 👤 Member for 15 years 4 months

Go to Project - Click on the Project - In the bottom go to settings

In settings go to Define critical Activities and mention the Total Float less than or equal to = which which would be considered as Critical

Featured Partner

Top Posters

Jeamiell Ostrovsky
2 posts
Hamzah Ahmed
0 posts
Quinton van Eeden
3 posts
Sunchana Johnston
12 posts
Akram Hammam Mohamed
17 posts
Sagar Raut
14 posts
Patricio_aoa
0 posts
James Williams
75 posts
Philip Assou-Dodji
1 posts
jeoffrey reyes
15 posts