Primavera 8.2 - Negative Float Issue

Our team has run into an issue with negative float being calculated to a Level of Effort task.  Background: We work in a very large Integrated Master Schedule (IMS) that encompasses in excess of 30 individual projects.  These projects have multiple tasks that are logically linked from one project to another.

 

The current issue: I have a LOE that only has a SS relationship to a task within that project (with 0 Days Total Float) and a FF relationship to another task within that project (with 232 Days Total Float).  The problem is that the LOE indicates -620 Days Total Float.  There are no constraints (Start On or After, Finish On or After, etc.) assigned.  I must be missing something?

Featured Partner

Top Posters

Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts
Hamzah Ahmed
0 posts
Quinton van Eeden
3 posts
Sunchana Johnston
12 posts
Akram Hammam Mohamed
17 posts
Sagar Raut
14 posts
Patricio_aoa
0 posts
James Williams
75 posts