Primavera 8.2 - Negative Float Issue

Our team has run into an issue with negative float being calculated to a Level of Effort task.  Background: We work in a very large Integrated Master Schedule (IMS) that encompasses in excess of 30 individual projects.  These projects have multiple tasks that are logically linked from one project to another.

 

The current issue: I have a LOE that only has a SS relationship to a task within that project (with 0 Days Total Float) and a FF relationship to another task within that project (with 232 Days Total Float).  The problem is that the LOE indicates -620 Days Total Float.  There are no constraints (Start On or After, Finish On or After, etc.) assigned.  I must be missing something?

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts