Final EOT Entitlement Calculation

As per the delay anaysis total 4 months delay happened. Contractor is responsible for 3 months and owner responsible for 1 month. 

Is contractor entieled for time extension for this 1 month delay by owner.

How to calcuate final delay assessment after the cases like this?  

M
Mike Testro 👤 Member for 20 years 5 months

Hi Mohamed

If you are talking about overlapping delays the usual rule is that you will be awarded an EOT but no prolongation costs.

But the contract that you signed may not allow this.

Best regards Mike T.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts