FIDIC clause 20.1

Hi Everyone

Would notice legal and acceptable to the Employer / Board or a Court if a Contractor serves a notice to the Employer under FIDIC clause 20.1 for delay that has not yet occurred but likely to occur.

Cheers Tanveer

M
Mike Testro 👤 Member for 20 years 5 months

Hi Tanveer

A timely notice of delay is always acceptable.

Best regards

Mike T.