Hi Everyone
Would notice legal and acceptable to the Employer / Board or a Court if a Contractor serves a notice to the Employer under FIDIC clause 20.1 for delay that has not yet occurred but likely to occur.
Cheers Tanveer
Hi Everyone
Would notice legal and acceptable to the Employer / Board or a Court if a Contractor serves a notice to the Employer under FIDIC clause 20.1 for delay that has not yet occurred but likely to occur.
Cheers Tanveer
Thank you very much Mr. Testro
Hi Tanveer
A timely notice of delay is always acceptable.
Best regards
Mike T.