Calendar to be used for evaluating the impact of delay event

 

If need to evaluate the impact of delay event whereas, the contractual programme's calendar is a 6 working day, what calendar to be used in the relevant schedule which is to be used to produce the Impacted Schedule, do I have to change the contractual programme calendar into (7 working day calendar) or the Impacted schedule shall preserve the contractual 6 working day calendar?

A
Ammar Al-Saket 👤 Member for 14 years 7 months

Thanks a lot Mike,

Just to make sure that I've understood you correctly; say I have the following situation:

  • project has 3 activities namely: A,B & C linked Finish-to-Start relationship.
  • activity D is the project completion "finish-milestone".
  • calendar used for all activities is 5 working day calendat
  • Time for Completion of the Works is counted in calendat days
  • An excusable and compensable delay event had delayed the completion date of the project (milestone D) for 4 weeks (20 working days) 
  • So, is the compensation for 28 days or for 20 days?

Thanks again

Ammar

M
Mike Testro 👤 Member for 20 years 5 months

Hi Ammar

Retain the working calendar for the impacted tasks.

The shift of the end date demonstrating delay should be represented by a hammock which has a 24/7 calendar.

The impacted events in the fragnet may have different calendars as required.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts