If need to evaluate the impact of delay event whereas, the contractual programme's calendar is a 6 working day, what calendar to be used in the relevant schedule which is to be used to produce the Impacted Schedule, do I have to change the contractual programme calendar into (7 working day calendar) or the Impacted schedule shall preserve the contractual 6 working day calendar?
Calendar to be used for evaluating the impact of delay event
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Hi Amar
28 calendar days.
Best regards
Mike Testro
Thanks a lot Mike,
Just to make sure that I've understood you correctly; say I have the following situation:
Thanks again
Ammar
Hi Ammar
Retain the working calendar for the impacted tasks.
The shift of the end date demonstrating delay should be represented by a hammock which has a 24/7 calendar.
The impacted events in the fragnet may have different calendars as required.
Best regards
Mike Testro