It all depends on what it says in your Sub-Contract as to when your LDs may kick in.
I am puzzled by your statement that you will finish on time but your late start will delay other sub-contractors.
It seems that your work is part of a chain of staggered workfronts that woul be typical of a high rise building - some further detail would be helpful.
In this case it would seem that you may be liable for a disruption claim from the other sub-contractors but this can only be chanelled through the Main Contractor.
My current advice would be to keep quiet and keep good records.
Member for
19 years 10 monthsHi CH L It all depends on
Hi CH L
It all depends on what it says in your Sub-Contract as to when your LDs may kick in.
I am puzzled by your statement that you will finish on time but your late start will delay other sub-contractors.
It seems that your work is part of a chain of staggered workfronts that woul be typical of a high rise building - some further detail would be helpful.
In this case it would seem that you may be liable for a disruption claim from the other sub-contractors but this can only be chanelled through the Main Contractor.
My current advice would be to keep quiet and keep good records.
Best regards
Mike Testro