work program revision in accordance with approved E.O.T

Member for

19 years 10 months

Hi Vand



Welcome to PP



Since the EoT was awarded while work is in progress the Impacted As Planned is the most likely method to have been used.



The other 3 are applicable to Forensic Analysis.



Best regards



Mike Testro

Member for

15 years 5 months

Mai,



It all depends on what approach youve used to claim EoT. If it is indeed Impacted as planned then Mike’s reccommendation will hold true. If another type of approach has been used to claim extension,then ur baseline will be in accordance to that EoT.





Regards



Vond Kye

Member for

19 years 10 months

Hi Mai



Save the baseline in a new file - add in the delay events that caused the EoT to show the agreed likely completion date.



Save the file as Baselie EoT 1 and use that file for future contract progress and updates.



Best regards



Mike Testro