Forensic Claims Analysis Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Sun, 2010-05-30 10:14 Permalink RE: work program revision in accordance with approved E.O.T Hi Vand Welcome to PP Since the EoT was awarded while work is in progress the Impacted As Planned is the most likely method to have been used. The other 3 are applicable to Forensic Analysis. Best regards Mike Testro Member for 15 years 5 months Member for 15 years 5 months Submitted by Vond Kye on Sun, 2010-05-30 09:24 Permalink RE: work program revision in accordance with approved E.O.T Mai, It all depends on what approach youve used to claim EoT. If it is indeed Impacted as planned then Mikes reccommendation will hold true. If another type of approach has been used to claim extension,then ur baseline will be in accordance to that EoT. Regards Vond Kye Member for 15 years 8 months Member for 15 years 8 months Submitted by Mai Tawfeq on Sun, 2010-05-30 07:49 Permalink RE: work program revision in accordance with approved E.O.T thanks. Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Sun, 2010-05-30 07:36 Permalink RE: work program revision in accordance with approved E.O.T Hi Mai Save the baseline in a new file - add in the delay events that caused the EoT to show the agreed likely completion date. Save the file as Baselie EoT 1 and use that file for future contract progress and updates. Best regards Mike Testro Log in or register to post comments
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Sun, 2010-05-30 10:14 Permalink RE: work program revision in accordance with approved E.O.T Hi Vand Welcome to PP Since the EoT was awarded while work is in progress the Impacted As Planned is the most likely method to have been used. The other 3 are applicable to Forensic Analysis. Best regards Mike Testro
Member for 15 years 5 months Member for 15 years 5 months Submitted by Vond Kye on Sun, 2010-05-30 09:24 Permalink RE: work program revision in accordance with approved E.O.T Mai, It all depends on what approach youve used to claim EoT. If it is indeed Impacted as planned then Mikes reccommendation will hold true. If another type of approach has been used to claim extension,then ur baseline will be in accordance to that EoT. Regards Vond Kye
Member for 15 years 8 months Member for 15 years 8 months Submitted by Mai Tawfeq on Sun, 2010-05-30 07:49 Permalink RE: work program revision in accordance with approved E.O.T thanks.
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Sun, 2010-05-30 07:36 Permalink RE: work program revision in accordance with approved E.O.T Hi Mai Save the baseline in a new file - add in the delay events that caused the EoT to show the agreed likely completion date. Save the file as Baselie EoT 1 and use that file for future contract progress and updates. Best regards Mike Testro
Member for
19 years 10 monthsRE: work program revision in accordance with approved E.O.T
Hi Vand
Welcome to PP
Since the EoT was awarded while work is in progress the Impacted As Planned is the most likely method to have been used.
The other 3 are applicable to Forensic Analysis.
Best regards
Mike Testro
Member for
15 years 5 monthsRE: work program revision in accordance with approved E.O.T
Mai,
It all depends on what approach youve used to claim EoT. If it is indeed Impacted as planned then Mikes reccommendation will hold true. If another type of approach has been used to claim extension,then ur baseline will be in accordance to that EoT.
Regards
Vond Kye
Member for
15 years 8 monthsRE: work program revision in accordance with approved E.O.T
thanks.
Member for
19 years 10 monthsRE: work program revision in accordance with approved E.O.T
Hi Mai
Save the baseline in a new file - add in the delay events that caused the EoT to show the agreed likely completion date.
Save the file as Baselie EoT 1 and use that file for future contract progress and updates.
Best regards
Mike Testro