work program revision in accordance with approved E.O.T
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Hi Vand
Welcome to PP
Since the EoT was awarded while work is in progress the Impacted As Planned is the most likely method to have been used.
The other 3 are applicable to Forensic Analysis.
Best regards
Mike Testro
Mai,
It all depends on what approach youve used to claim EoT. If it is indeed Impacted as planned then Mikes reccommendation will hold true. If another type of approach has been used to claim extension,then ur baseline will be in accordance to that EoT.
Regards
Vond Kye
thanks.
Hi Mai
Save the baseline in a new file - add in the delay events that caused the EoT to show the agreed likely completion date.
Save the file as Baselie EoT 1 and use that file for future contract progress and updates.
Best regards
Mike Testro