Greetings everyone,
May i ask your expertice about AstaPP?
WH is 8:00am - 5:00pm, Building Construction, Creation of BL Sched.
I want to use the Task Work feature in AstaPP, while doing it, i noticed that it makes my activies to finish in-between the day which allows the successor to start on the same day. I want the successor to start the next day even if the predeccessor is already finished before the end of the working hours.
May I ask someones assistance on this.
Thank you very much in advance.
Prince
Thank you on your immediate reply Sir Vladimir Liberzon & Sir Ben Taunt.
Hi Prince,
Go to the Properties of the Task (right click on the task), navigate to Constraints options and select "Start on new day". This will force the task to always start the next day, regardless of when in the day your predeccessor finishes.
[[wysiwyg_imageupload:8525:]]
Thanks,
Ben @ Asta Powerproject
Hi Prince,
Go to the Properties of the Task (right click on the task), navigate to Constraints options and select "Start on new day". This will force the task to always start the next day, regardless of when in the day your predeccessor finishes.
[[wysiwyg_imageupload:8525:]]
Thanks,
Ben @ Asta Powerproject
I don't know if Asta permits to assign special calendar to dependency lag.
If yes, assign to lag 24 hours per day calendar and make it 8 hours (if your work day lasts 8 hours).
With this lag the successor will always start in the next day.