Using Task Work Feature

Member for

5 years 7 months

Thank you on your immediate reply Sir Vladimir Liberzon & Sir Ben Taunt.

Member for

13 years 9 months

Hi Prince,

Go to the Properties of the Task (right click on the task), navigate to Constraints options and select "Start on new day". This will force the task to always start the next day, regardless of when in the day your predeccessor finishes.

[[wysiwyg_imageupload:8525:]]

Thanks,

Ben @ Asta Powerproject 

Member for

13 years 9 months

Hi Prince,

Go to the Properties of the Task (right click on the task), navigate to Constraints options and select "Start on new day". This will force the task to always start the next day, regardless of when in the day your predeccessor finishes.

[[wysiwyg_imageupload:8525:]]

Thanks,

Ben @ Asta Powerproject 

Member for

24 years 9 months

I don't know if Asta permits to assign special calendar to dependency lag.

If yes, assign to lag 24 hours per day calendar and make it 8 hours (if your work day lasts 8 hours).

With this lag the successor will always start in the next day.