Early & Late "banana curve"

Hi - I'm looking to produce banana curves (early and late date envelope) as part of the project controls suite of metrics using Powerproject. I used to produce these in P6 using activity count resource in the Resource Assignment spreadsheet window and then exported to Excel for graphing.

I've assigned an activity count to the remaining activities in the programme as a consumable resource but then am drawing a blank when it comes to getting the AC spread for the planned early and late date (ideally in a tabular fashion).

Has any one any ideas/done something similar?

Many Thanks

A
Andrew Owenson 👤 Member for 18 years

Hi Chris

 

You could use the EA Reporter under the Project Tab. Make sure you select the duration as the quantity to report on. You will need to baseline the project first.

When you get to the baselines section report against the baseline you just did - ASAP baseline (top selection), and make sure that "use float end dates from my ASAP baseline is selcted (bottom selection). Choose current view & run.

 

The results will depend on how well your netwrok is linked.

 

Good luck

 

Regards

 

Andrew

Forum Sponsor

Top Posters

Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts