Early & Late "banana curve"

Hi - I'm looking to produce banana curves (early and late date envelope) as part of the project controls suite of metrics using Powerproject. I used to produce these in P6 using activity count resource in the Resource Assignment spreadsheet window and then exported to Excel for graphing.

I've assigned an activity count to the remaining activities in the programme as a consumable resource but then am drawing a blank when it comes to getting the AC spread for the planned early and late date (ideally in a tabular fashion).

Has any one any ideas/done something similar?

Many Thanks

A
Andrew Owenson 👤 Member for 18 years 1 month

Hi Chris

 

You could use the EA Reporter under the Project Tab. Make sure you select the duration as the quantity to report on. You will need to baseline the project first.

When you get to the baselines section report against the baseline you just did - ASAP baseline (top selection), and make sure that "use float end dates from my ASAP baseline is selcted (bottom selection). Choose current view & run.

 

The results will depend on how well your netwrok is linked.

 

Good luck

 

Regards

 

Andrew

Featured Partner

Top Posters

Ashkan Mohammadi
0 posts
Jeroen De Bauw
0 posts
Senior Planning Engineer
0 posts
Kristian Mcwilliams
1 posts
dagogo dan - jumbo
2 posts
Alex Lyaschenko
27 posts
James Williams
75 posts
xerxes
0 posts
edwin
0 posts
jhalluk69
0 posts