Project:- MID COUNTRY REFINERY PROJECT (MCRP)
Client:- PAK-ARAB REFINERY COMPANY
AS PIPING SUPERVISOR (TESTING CO-ORDINATOR)
Major Responisibilities
I. Fabrication & Erection of Process & Utility Piping.
II. Preparation and approval of test packs. (1127 Nos).
III. Preparation of schedule for testing.
IV. Conduct the hydro / pneumatic tests, flushing & air blowing.
V. Supervision of Punch killing work.
Client:- PAK-ARAB REFINERY COMPANY
AS PIPING SUPERVISOR (TESTING CO-ORDINATOR)
Major Responisibilities
I. Fabrication & Erection of Process & Utility Piping.
II. Preparation and approval of test packs. (1127 Nos).
III. Preparation of schedule for testing.
IV. Conduct the hydro / pneumatic tests, flushing & air blowing.
V. Supervision of Punch killing work.