What is needed to come up with a production rate?
A duration of time, the manhours involved, and an amount of work produced?
This section is here to document this. What information do you have that you can share?
Book navigation for Rates, Norms & Durations
-
-
-
-
-
-
-
-
Rates, Norms & Durations
-
-
-
-
Comments
Wood Doors and Frames Door Frames and Trim Single Exterior ea3mh/unitDouble Exterior ea6mh/unitSingle Interior ea3mh/unitDouble Interior ea4mh/unitSliding Door Frame ea4mh/unit Doors, Fit, Hand, and Lock Single Exterior ea5mh/unitDouble Exterior ea8mh/unitSingle Interior ea5mh/unitDouble Interior ea7mh/unitScreen Doors ea2mh/unit Metal Doors Single ea6mh/unitDouble ea9mh/unit Miscellaneous Doors Complete with Trim and Hardware Rolling, Manual Operated ea29mh/unitRolling, Motor Operated ea36mh/unitSliding, Manual Operated ea20mh/unitSliding, Motor Operated ea26mh/unitSliding, Fire ea19mh/unit Garage Doors Wood 16' X 7' ea8mh/unitAluminum 16' X 7' ea10mh/unitScuttles ea10mh/unitCaulking ft0.005mh/unit NOTES: 1. Includes jambs, stops, casings, and weather stripping. 2. Does not include sills or thresholds. 3. On wood doors, if power planes, hinge butt routers, and lock mortisers are used, use 0.75 multiplier on installation time. Window Installation Work Element Description Unit Man-Hours Per Unit Wood Windows Double Hung ea4mh/unitCasement, Single ea4mh/unitFixed, Wood Sash ea3mh/unitJalouse ea2mh/unitSkylights ea8mh/unit Metal Windows Casement Commercial Projected ea2mh/unitSkylights ea2mh/unitDouble Hung ea9mh/unitLouvers ea5mh/unitScreens ea2mh/unitVenetian Blinds ea2mh/unitWeatherstripping ea3mh/unitCaulking ft0.003 SUGGESTED CREW SIZE: Two to six BUs NOTES: 1. Installation includes drilling for fasteners, expansion shields, installing plugs, toggle bolts, blocking, hinges, locks, and other hardware.2. For special panic device for doors add three hours for single, four hours for double doors. TABLE 4-101. Glass and Glazing Work Element Description Unit Man-Hours Per Unit Small Panels 2-FT. Square or Less ft0.2mh/unit0.19 sg.m.- m21.7 Medium Panels 2- to 6-FT Square ft0.2mh/unit0.0185-to 0.557 sq.m. m21.8 Large Panels 6- to 10-FT Square ft0.2mh/unit0.557- to 1.0 sq.m. m22.3 Plate Glass Store Fronts 200- to 400- FT Square ft21.0mh/unit18- to 37 sq.m. m2226.1 NOTES: 1. Estimates are based on putty set installation: if installed with metal stops and rubber, double theman-hour figures; if vinyl set, snap-on triple man-hour figures; for insulated glass use 0.67 multiplier2. When glazing from outside using scaffolding or swinging staging, one man is required on the groundto support two glaziers; use 1.5 multiplier 3. For winter work add use 1.25 multiplier. 4. Do not air ship insulated glass units such as Thermopane, Twindow, etc., due to unequalpressurization.
For your requirement lads,
Hello all
Im new to this platform but am looking for some output rates for sprinkler installations in the UK. any and all help will be apprecieated
Hi, Has anyone got any information of Metsec output rates please
Hi,
It seems that the most of the rates here are equipment rates. do you have any rates for manpowered activities (e.g. manual excavation)
looking at the drainage outputs on here they don't seem to be that reliable? does anybody have an excel spreadsheet they would be able to send with some general drainage outputs?
hi,
Anyone having Manpower productivy norms excel file for MEP(Gulf), it will be very helful to me.
e-mail: [email protected]
I am struggling to see any logic behind the productions per hour on the drainage?
33m per hour for 150mm drainage in runs exceeding 30m or greater is impossible - unless installed via trenchless methods!
I calculate my drainage productions to include dig, bed and surround, pipe laying and backfilling compacting in accordance with the specification and would never price on more than 30 - 35m per DAY for a 150mm UPVC pipe at a depth not exceeding 1m.
What do the productions on here realte to and what do they include?
What geographical location is labor being executed? (remote/local port)
What is the weather conditions?
What type of industry?
Other particulars or need; Are there readily available resource (MP & DFL Equip/Consumables) ?
Please feel free to contact me at your convenience.
Once we come into mutual agreement, I will produce the needed excel loaded unit rates for your project/s need/s. Based on execution industry actuals.
Best regard,
JEPM LLC
Project Controls Engineer SME
Jacob Armstrong
409-457-7725
Are you in need still?
Jaocb Armstrong JEPM LLC 409-457-7725
Ya, I am waiting for comments. If you can give some feedback/ comments, it will greatly be useful.
Thanks/Regards,
Santhosh
Ya, I am waiting for comments. If you can give some feedback/ comments, it will greatly be useful.
Thanks/Regards,
Santhosh
Are you in need still?
Jaocb Armstrong JEPM LLC 409-457-7725
Hi all,
Can you comment on impact of crew design, i.e crew size and composition on productivity?
Thanks,
Santhosh
Dear all experts;
This data is very useful for me and thank you all. But i need construction labour rates as an excel file. If somebody has it and sen me i will very be thankful. Also can you please give a book advise for this issue.
Thank you all.
[email protected]
Dear all experts,
I need the productivity rates for Oil & Gas Project - Construction Trade like Sand Blaster, Fireproofer, Spray Painter, Scaffolder, Sheet Metal Fitter, Insulators and Welder.
I will be very thankful if excel file or PDF file of all production rates can be shared on my email address: [email protected]
Thank You
Can i get the production rate dia Inch for CHW pipes for example 20" pipe one joint require 3 hours .. Etc or if there is a formula followed to calculate the same knowing that its all sch STND
Thank you deeply, for the great effort you've been doing.
I just would like to pay your attention that the productivity rates are in a big need to the crew structure producing these rates.
Best Regards,
Thank you deeply, for the great effort you've been doing.
I just would like to pay your attention that the productivity rates are in a big need to the crew structure producing these rates.
Best Regards,
Thank you deeply, for the great effort you've been doing.
I just would like to pay your attention that the productivity rates are in a big need to the crew structure producing these rates.
Best Regards,
Dear all experts,
I need the productivity rates for first and second fixs for MEP work (HVAc, Firefighting and Plumbing).
Thank you
Dear all experts,
I need the productivity rates for first and second fixs for MEP work (HVAc, Firefighting and Plumbing).
Thank you
Good Morning,
The information avaialble here is very useful for me, thanks a lot.
I will be very thankful if excel file or PDF file of all prodcution rates can be shared on my email address: [email protected]
Thanks,
Vikas Budhiraja, PMP
Can anyone help me with the units used to measure progress of platfrom fabrication & welding?
Is it ok to USE ... Kg of steel fabricated or welded?
Can anyone help me with the units used to measure progress of platfrom fabrication & welding?
Is it ok to USE ... Kg of steel fabricated or welded?
Hi Guys,
Just like to know if we have productivity rate for glazing partitions..... also there is no productivity rate for plasterboard installation on the partitioning rates.
Thanks!
Ruel
S.N0
Activity
Productivity norms
Qty
Units
DUCTING:
1
Duct
1.2 – 1.5
Sqm/man/day
2
Insulation
3
Sqm/man/day
3
1 No - VAV
3
Sqm/man/day
4
1 No - ECV
2
Sqm/ man/day
5
1 No – Joint Insulation
0.4
Sqm/man/day
6
1 No - Flexible Duct
1
Sqm/man/day
7
1 No - Plenum
1
Sqm/man/day
8
1 No - MSFD
2
Sqm/man/day
9
1 No - VCD
1
Sqm/man/day
10
Pressure Test per 25 Sqm ducting
4.5
Sqm/man/ day
11
Multipurpose Supports – 4 No
1.5
Sqm/man/day
12
Grills & Diffusers
6
No’s / Man/ day
13
Linear Slot Diffuser
6
Rm / Man / day
Kindly note that here ducting is inclusive Support fixing + Cleat fixing + Sealant application
CHW PIPE:
1
1" – 2" dia
7.5
Rm/man/day
2
2" - 3"dia
5
Rm/man/day
3
4"dia
2.5
Rm/man/day
4
6"dia
1.5
Rm/man/day
5
8"dia
1.2
Rm/man/day
6
10"dia
1
Rm/man/day
7
CHW Pipe Insulation
15
Rm/man/day
8
Pressure Test for 100 Rm
3
man/day
9
Valve Package
1.5
Man / day / unit
Kindly note that here Chilled water piping is inclusive of Support fixing
S.N0
Activity
Productivity norms
Qty
Units
ELECTRICAL/ELV
1
Conduit
16
Rm/man/day
2
Wiring
30-40
Rm/man/day
3
Cable tray
5-6
Rm/man/day
4
Trunking
8-10
sq.m/man/day
5
DB Installation
1
Nos/man/day
6
DB Termination
1
Nos/man/day
7
Final Fix Accessories
8
Nos/man/day
8
Light points
8
Nos/man/day
PLUMBING
1
Water supply pipe installation
5
Rm/man/day
2
Drain pipe installation
3
Rm/man/day
Kindly note that Piping Installation is inclusive of Support fixing
Hi all,
I am also facing problem in sourcing MEP labout production rate for Middle East Region. Anyone can help?
regards,
Kevin
Hi Frendz ...
I like this section this is helping me in may ways ..but i am facing problem when it comes to productivity rates given without resources, as what resource should i consider if i want to use these rates please help .......
regards,
Khan