Planned % not matching with Actual

please help, planned % not matching with actual % , i dont know how.\

screenshot_2024-10-08_200024.png

[[wysiwyg_imageupload::]]

J
Jerome Odeh 👤 Member for 22 years 5 months

Your screenshot shows the Planned % & Actual % do match where the start & finish dates are the same.

If you are worried that Planned % comes with decimals while Actual % doesn't, it's because the Planned % is calculated using Custom Field formula while Actaul % is a default Microsoft Project field.

This blog post might help you. Microsoft Project Baseline Percent (%) with Weighted Summary Roll-up