Distribution by change in Date - Excel

Hello Team,

Need your support in solving a proble. I have made a table with start date (A) and Finish date (B), The total Quantity (C) is divided by the durtation to give the per day quantity (D). Now I have per month cut of date (E, F, G, H).

Can anyone propose a formula for E. F, G, H, where the quantity would change when I change the start (A2) and finish (B2) based on the date in E2, F2, G2 and H2.

quantity.png

J
Jithin Kambhikanam 👤 Member for 15 years 2 months

Hi All,

Can I have few more ideas.

Like by changing the date it should automatically distribute the quantity per month.

 

Thanks

Jithin

B
benadjal redouane 👤 Member for 7 years 7 months

Hello, please find to attached file.

the quantity change when you change the start date and finish date and the dates in E2, F2, G2 and H2 change also.

Your exemple:                        
Start Finish Duration Total Qty Per Day 27/09/2024 25/10/2024 29/11/2024 27/12/2024 Total
Duration 1 Qty 1 Duration 2 Qty 2 Duration 3 Qty 3 Duration 4 Qty 4
09/09/2024 27/12/2024 110,00 1000 9,09090909 19,00 172,727273 28,00 254,545455 35,00 318,181818 28,00 254,545455 1000
                           
Change date start and finish                      
Start Finish Duration Total Qty Per Day 29/10/2024 26/11/2024 31/12/2024 25/02/2025 Total
Duration 1 Qty 1 Duration 2 Qty 2 Duration 3 Qty 3 Duration 4 Qty 4
11/10/2024 25/02/2025 138,00 1000 7,24637681 19,00 137,681159 28,00 202,898551 35,00 253,623188 56,00 405,797101 1000

if you need execl file please send me.

my ID Email is: [email protected]

have a nice day.

BENADJAL Redouane

Project engineer (Algeria)

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts