Multiple imports of risks to Primavera P6

D
Dejan Kezic 👤 Member for 8 years 3 months

Hi everyone,

Is there solution ti import (through Excel) risks to large number of activities in P6 schedule?

Similar to importing of activities and/or resources, I would like to define several different risks and then instead of using manual method in P6 to export file to Excel, then prepare it for importing by coping risks to different activities and return it through import.

I have tried it, but I can not find Risks in Available Options in Export dialogues.

 

Thank you in advance!

B
Bhavinbhai Lakhani 👤 Member for 2 years 1 month

Hello Dejan,

 

I think currently, Primavera (P6) does not natively support exporting and importing risks directly through Excel in the same way it does for activities and resources. To achieve this, you typically need to manage risks within P6 itself rather than using Excel as an intermediary for direct risk import.

 

Hope it would help you.

Thanks

Featured Partner

Top Posters

GeoVe
0 posts
Ashkan Mohammadi
0 posts
Jeroen De Bauw
0 posts
Senior Planning Engineer
0 posts
Kristian Mcwilliams
1 posts
dagogo dan - jumbo
2 posts
Alex Lyaschenko
27 posts
James Williams
75 posts
xerxes
0 posts
edwin
0 posts