Schedule % Complete in P6 is Duration based.

Member for

10 years 6 months

If in a schedule, contractor has not loaded cost, how can we get Schedule% at WBS level?

Member for

10 years 6 months

If in a schedule, contractor has not loaded cost, how can we get Schedule% at WBS level?

Member for

10 years 6 months

If in a schedule, contractor has not loaded cost, how can we get Schedule% at WBS level?

Member for

10 years 6 months

If in a schedule, contractor has not loaded cost, how can we get Schedule% at WBS level?

Member for

10 years 6 months

If in a schedule, contractor has not loaded cost, how can we get Schedule% at WBS level?

Member for

10 years 6 months

If in a schedule, contractor has not loaded cost, how can we get Schedule% at WBS level?

Member for

14 years 5 months

Thank u David Kelly for ur sharing. So  much appreciated

Member for

14 years 5 months

Hi Rodel Marasigan

Thank u for ur detail explanation. So much appreciated.

so, Schedule%complete for activity is time-based (duration based)

     Schedule % complete for WBS is cost based

I still cannot brain why P6 use duration based to calculate the plan% for activities. of which it is well known and agreed by all the planning engineers & schedulers that using duration is the least accurate for us to get the %.

 

Anyway thank u so much Mr Marasigan

 

 

 

 

 

 

Member for

19 years

Hi Suhaila,

The activity schedule % complete specifies how much of the activity's baseline duration has been completed so far. Computed based on where the current data date falls between the activity's baseline start and finish dates. If the data date is earlier than the baseline Start, the Schedule % Complete is 0. If the data date is later than the baseline Finish, the Schedule % Complete is 100. The Schedule % Complete indicates how much of the activity duration should be currently completed, relative to the selected baseline.

P6 calculate schedule % complete on an activity based on cost distribution in linear for each activity duration but for WBS or summary it follows the cost distribution total for all activities using the resource curve or future buckets.

See sample below:

Task 1 - 10 day duration

Calendar Mon-Fri 8hrs per day (8:00-4:00)

Schedule-Complete

The sample Task 1 had a resource assigned having backloaded resource curved. I moved the data date to Friday 5:00PM, 11Mar2022 without scheduling (F9) to show the Schedule % complete based on baseline duration of activity which is equivalent to 50% (5days/ 10 days) but the summary or WBS heading is showing the backloaded Schedule % complete @ 35% on the 5th day.

Note: Schedule % complete on summary will not show if you don't have cost assigned to resources.

Member for

21 years

Schedule % complete is from the baseline. It is cost based. You could (in error) have the current project set to the baseline.

I only use two percent completes in any layout:

oN eof either Performace % complete (BCWP) or Perforamce % complete Labour ( BQWP)

and

Schedule % complete (BCWS)