Primavera P6 activity Bar

Dear sirs, I have recently moved from MSP back to Primavera P6.

I am trying to prevent the activity bar from reducing in size when using duration % i.e if the bar covers a 1 month duration with  known start and finish date and i apply  20% progress, the bar reduces in size by 20%. and if i apply 100% it ieffectively dissappears I have worked out that if i use fixed work the durtion remains the same size but if I apply some progress the work units do not reduce.

I dont recall having this issue in MSP?- What am i doing wrong or using incorrectly - i dont have anyone to ask ?

 

Andy 

D
david kelly 👤 Member for 10 years 4 months

What you are describing is what the bar dialogue call the ‘Remaining’ bar. There is no ‘Activity’ bar

If you want to draw a bar from the Early start to Early finish – unaltered by progress the timescale you want in the second column of the barchart dialogue in ‘Plan Bar’

I recommend a wee P6 dates refresher. Google: Ron Winter Primavera Dates

Forum Sponsor

Top Posters

Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts