I am trying to import and MS project file (MPX) to Primavera P6 and after a successful import, the start/finish dates are not imported in P6. If the activity is 100% completed, I only have the A in the start/finish cell in P6.
Any thoughts pls?
Tasks dates not imported in P6
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Rox,
P6’s main purpose is to calculate start and finish dates. Specifically Early, remaining early, late, remaining late and planned start and finish. It is a long time since I imported an MPX file, but when importing a spreadsheet you cannot import any of these dates, you can only import dates that are input to the schedule calculations. To populate date fields in P6 you need to schedule.