Dear All,

How do you make specific activities in p6 start only on Monday irrespective of their predecessor finishing day. I don't want to assign constraints.

R
Rafael Davila 👤 Member for 22 years 4 months

2023-07-17-16-34-05 Figure 1

2023-07-17-16-41-36 Figure 2

For a better view hover the figures and click.

Figure 1 shows how with calendar lags can be done. This does not require additional milestone.

Figure 2 shows how with activity lags can be done. This requires an additional intermediate milestone.

The special calendar was created with a very short duration very early on Monday, 0 duration on the remaining days of the week.

V
Vladimir Liberzon 👤 Member for 25 years 4 months

Create zero duration activities with calendars that have only one work hour in a week on Monday night.

Add these activities as preceding to your activities that must start on Mondays.

All inbound dependencies to your activities starts must become preceding to created zero duration activities.

This advice will not work if your activities have predecessors to their finish points.

Forum Sponsor

Top Posters

Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts