Resource Spreading Primavera

Hi All,

I have an activity in Primavera with a duration of 15 Days but I need the resource till 10 the Day

Is there a way to spread the budgeted resource to only the 10th Day ?

 

Thansk

Jithin 

D
david kelly 👤 Member for 10 years 3 months

Jithin,

 

Yes there is. The resource assignment record has fields which you can see in the Activity Details forms, for Resource lag (how long after the activity starts the resource is required, and resource duration.

BUT you have to be very careful with the Project Level 'Drive activity dates by default' switch, if a resource (e.g. 'Get Paid') is not within the sceduled start and finish date of the activity. Your example of (I think) a resource required for the first 10 of fifteen days will not change the activity duration

D
david kelly 👤 Member for 10 years 3 months

Jithin,

 

Yes there is. The resource assignment record has fields which you can see in the Activity Details forms, for Resource lag (how long after the activity starts the resource is required, and resource duration.

BUT you have to be very careful with the Project Level 'Drive activity dates by default' switch, if a resource (e.g. 'Get Paid') is not within the sceduled start and finish date of the activity. Your example of (I think) a resource required for the first 10 of fifteen days will not change the activity duration

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts