Task mode in activity Zero

Hi Helpers,

Is it a way to change TASK MODE for activity ZERO (Project summary)?

Image removed.

 

Regards,

Alex Lyaschenko 

R
Rodel Marasigan 👤 Member for 19 years 8 months

It is not possible. It always default to Auto and cannot be manuall. It always calculate overall project duration even with no task.