Duration Type of Fixed Units not working properly

Hi All,

 

I am using Duration Type of Fixed Units for some activities. The Units are from the Cost Estimate. When I allocate a Resource to the Activity, the Duration changes accordingly to match the Resource Availability (12h/D).

 

So an activity with 120 hours as Units generates a Duration of 10 days when the Resource is assigned.



But when I add a second Resource ( the same Resource now on the activity twice), the Units double and the duration remains the same.

 

Which is exactly the opposite of what should happen, Units should remain at 120 hours and the Duration should shrink to 5 days.

 

Any ideas what I am doing wrong?

R
Rodney Jones 👤 Member for 13 years 11 months

Rodel to the Rescue once again. Yes, I knew I was forgetting a switch somewhere. Thanks again Mate. All fixed and working as expected now.

R
Rodney Jones 👤 Member for 13 years 11 months

Rodel to the Rescue once again. Yes, I knew I was forgetting a switch somewhere. Thanks again Mate. All fixed and working as expected now.

R
Rodney Jones 👤 Member for 13 years 11 months

Rodel to the Rescue once again. Yes, I knew I was forgetting a switch somewhere. Thanks again Mate. All fixed and working as expected now.

R
Rodney Jones 👤 Member for 13 years 11 months

Rodel to the Rescue once again. Yes, I knew I was forgetting a switch somewhere. Thanks again Mate. All fixed and working as expected now.

R
Rodney Jones 👤 Member for 13 years 11 months

Rodel to the Rescue once again. Yes, I knew I was forgetting a switch somewhere. Thanks again Mate. All fixed and working as expected now.

R
Rodney Jones 👤 Member for 13 years 11 months

Rodel to the Rescue once again. Yes, I knew I was forgetting a switch somewhere. Thanks again Mate. All fixed and working as expected now.

R
Rodel Marasigan 👤 Member for 19 years 7 months

Hi Rod,

If  you use Fixed Units on Duration type, therefore duration will follow on Resources availability when assigning resources.

Ex: Duration Type: Fixed Units

      % Complete Type: Duration

     Calendar working hours : 12hrs/day

If the activity has 10days duration when assigning resources the resource will automatically populated as 120hrs. If the resource units change to 96hrs, the activity duration will automatically change to 8 days.

If you added a new resource, the activity duration will change based on Resource Assignment setting at User Preference -->Calculation tab --> Resource Assignments

When adding or removing multiple resource on activity:

- Preserve the unit, duration, and unit/time for existing assignments

- Recalculate the Unit, Duration and Unit/Time for existing assignments based on the activity Duration type

If Preserve is selected, the behaviour of duration and units will be the same as is and will not change

If Recalculate is selected, the behaviour of duration and units will be acording to duration type.

On your case, it seems that the Preserve is selected on your settings.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts