Primavera running slow, for example when I delete activities it take 1.5 minutes even on small project. It is the only program that is that laggy or slow. I have used system utility programs in the fast and generally find them pretty dangerous - so I think it would be good if I find out what in particular effects P6 the most.
Primavera running slow, for example when I delete activities it take 1.5 minutes even on small project
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
I have similar problem with my standalone installation. I use SQLite and I have 81 projects in the database so far.
John,
Which database, and where is it (eg, SQLlite on my hard disk)
How much data - no of projects, number of activities, number of UDFs
Is this all of a sudden, or has performance been gradually getting worse?