Max units per time not matching "Limit" line in recourse usage profile bar chart

H
Huss PS 👤 Member for 3 years 10 months

Hi All,

 

I am using P6 V21.

"Limit" line in "Reosrce usage profile" window it is showing above 50h/d (Max units/time set when adding resource).

Has anyone experience similar issue? What could be the reason? and how to fix it?

 

PS: I tried to upload snapshot but unable to see images or load images on this website. probably becasue it's not https. If i can get help on this as well, that would be great.

Thanks 

H
Huss PS 👤 Member for 3 years 10 months

It Worked!!! 

You were correct. 

I deleted both calenders and added again. 

Thanks alot.

H
Huss PS 👤 Member for 3 years 10 months

I checked that again. Calender for both activities and resources are same.

see below snapshot.

[[wysiwyg_imageupload:8277:]]

D
david kelly 👤 Member for 10 years 3 months

So, you think the llimit should be 50, but it is really 63?

 

Sounds like a Resource Calendar issue

D
david kelly 👤 Member for 10 years 3 months

Can you double-click on one of the histogram bars, and report back the figures?

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts