Resource Driven Critical Path Visibility

Does anyone already have experience with this Primavera feature annonced in 21.12 release?   Resource Driven Critical Path Visibility.To aid in the resolution of delayed critical paths before they become project over-runs, P6 Professional can show:- Activities on up to 30 activity-driven critical paths, calculated on the forward pass, backward pass, or forward and backward passes (with or without resource leveling).- The activities on up to 30 resource driven critical paths, calculated on the backward pass with resource leveling. How it actaully work?Does anyone has an example? Have Oracle fixed the 'incorrect Total Float' bug when schedule is levelled?  

R
Rodel Marasigan 👤 Member for 19 years 7 months

Hi Vladimir,

As far as I'm aware, P6 only calculates Activity float path and not Resource float path.

V
Vladimir Liberzon 👤 Member for 25 years 4 months

Rodel,

what do you mean by the float path?

If activities have different calendars their floats would be different even if they belong to the same path.

Besides, as I showed in the example in my previous post, P6 calculates wrong resource constrained floats and shows wrong resource constrained critical path.

Was it fixed in version 21?

R
Rodel Marasigan 👤 Member for 19 years 7 months

Currently, I am using it to show the Activity critical path (Float Path) of the selected activity. In the toolbar, you can activate Activity Critical Path Toolbar. By default, it calculate the float path using backward pass of selected activity. If you select the start milestone of the program and click forward pass, it will display the activity forward pass float path. You can increase the number of activity criticality (float path). If the level resource is used, it used the resource level float path of selected activity, forward or backward pass (which ever is selected) or both.

 

V
Vladimir Liberzon 👤 Member for 25 years 4 months

I am curious if P6 leveling was improved in version 21.

Look at the schedule below, created with P6 v.20

P6floats

Notice that the last project activity Check Support has 20 days total and free float,

activities Develop technical requirements and Develop functional requirements have 13 days total floats though both are critical.

Critical activities do not create a path though in this simple schedule all activities and resources use the same calendar and no constraints are applied except resource availability constraints.

If nothing changed resource constrained total floats and resource critical path in P6 v.21 can be misleading.

D
david kelly 👤 Member for 10 years 3 months

I shall probably help my first client migrate to v21 this month. As always, Ed Harris has a good explanation of what this does. I am just not clear how, without a fully-functioning Resource Levelling facility, this helps? Without proper control of splitting under resource levelling, I currently have no clients using it. A cynic (mea culpa) would suggest this new facility extends cute Layout filtering, without actually improving the core arithmetic.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts