I have 2 baselines and i need to compare the Labour units for both with the current schedule.
How can i get the labour units for both of these baselines?
From below snapshot under "Units" both of the highlighted options are giving the same value.
TIA.
you can have up to 3 different baselines
The colums BL project Labour Units and BL1 project labour units. You have to declare a Project and Primary (BL1) baseline in the Assign Baselines dialogue