Is there a technical name for delay caused by not being able to work as scheduled? for example if something is FS instead of SS?

Is there a technical name for delay caused by not being able to work as scheduled? for example if something is FS instead of SS? (for example thought could start steel same time as concrete but had to wait until done.)  "Out of Sequence Delay" or "Logic Error Delay" or "Planning Delay"?

A
Alex Lyaschenko 👤 Member for 14 years 9 months

If a schedule has SS instead of FS (or any other combination) it is just a schedule quality issue that only could be solved by maturing schedule development process. 

A
Alex Lyaschenko 👤 Member for 14 years 9 months

If a schedule has SS instead of FS (or any other combination) it is just a schedule quality issue that only could be solved by maturing schedule development process. 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts