Way just to show the critical or driving activity connector lines in P6? (like we could in suretrak 20 yrs ago?
(When is P6 going to incorporate AEC construction features instead of IT/programmers turtle pace guesses at features?)
Way just to show the critical or driving activity connector lines in P6? (like we could in suretrak 20 yrs ago?
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
A schedule to be viable must clear all constraints.
In complex schedules with hundreds of resources and activities:
Simple scheduling without resource leveling.
After resource leveling.
I am not sure P6 will provide the missing information but maybe you can see in a column the available information regarding hard link drivers. Please take a look at the following link I hope will be of help.
Driving Predecessors Report in Primavera P6 - Project Controls Services
Best Regards, Rafael
easy first fiiter for the critical path and then turn on the relationship lines
for the full schedule you can use the visualizer as Santosh suggested
Alternatively in P6 you can select Trace logic on View--> Show on Bottom --> Trace Logic. You can change the Trace Logic options to number of predecessor and successor level to show. All driving critical activities have red connectors, driving non-critical is solid connectors and non-driving is dotted connectors.
John, No way to do this in the P6 client.
In P6 Visualizer, There are options to show driving relationships only and to then set the thickness for:
But then I've never used P6 Visualizer in anger so no idea what its capable of.