Progressing S Curve

R
Raj Maurya 👤 Member for 21 years 10 months

First update the activities which are in progress or completed. then put the status date in project info & update the project. Activities not completed or in progress will be resheduled from the status date according to dependencies but be carefull if you have set up constraints. May be possible your project complettion will extend and if you want end date keep the same adjust it increasing resources if it is resource driven.

Based on this revised shedule you can create revised S curve.