How to populate the Activityspread Table without the SDK or the API.

Is there a method to populate these tables:

  1. ACTIVITYSPREAD
  2. EPSSPREAD
  3. PROJECTSPREAD
  4. RESOURCEASSIGNMENTSPREAD
  5. RSRCROLEASGNMENTSPREAD
  6. WBSSPREAD

without the help of the SDK or the API?

Thanks in Advance.

M
Mohammed Ali 👤 Member for 8 years 2 months

I would like to draw the activity usage profile for any group of activities and for any project without the help of the P6.

The parser has no relation with what we speak about.

M
Mohammed Ali 👤 Member for 8 years 2 months

I would like to draw the activity usage profile for any group of activities and for any project without the help of the P6.

The parser has no relation with what we speak about.

R
Rodel Marasigan 👤 Member for 19 years 7 months

You have two options:

1) Create a layout in P6 using activity spread or resource spread then use copy and paste function to excel

2) Run these timespread tables in P6 Report with output to .csv then open in excel.

Alternative options is for programmer and software developer:

Create a program that automate these timespread in excel using the open database table of P6.

M
Mohammed Ali 👤 Member for 8 years 2 months

Hi Zoltan

Thank you for your reply.

These are the all features of Ranga:

1. import xer in excel

2. color your wbs

3. group by wbs

4. gantt chart by shape

5. gantt chart by cell format

6. create wbs dictionary

7. create resource dictionary

8. create activity code dictionary

9. extract calendar

Where the spread tables can be found?

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts