Hello All,
Need a help.
A formula to calulate the % duration complete based on IF OR function in excel
Today = (D)28-May-22ItemABDuration% CompleteItem 123-May-2228-May-226B=D,100%, A<D,B>A,(D-A+1)/(B-A+1)Item 225-May-221-Jun-228
Thanks
Jithin
Hello All,
Need a help.
A formula to calulate the % duration complete based on IF OR function in excel
Today = (D)28-May-22ItemABDuration% CompleteItem 123-May-2228-May-226B=D,100%, A<D,B>A,(D-A+1)/(B-A+1)Item 225-May-221-Jun-228
Thanks
Jithin
glad I could help but my formula was correct based on what you had
you had A<D
NOT A>D or B<D
was not excalty sure I but I did think your paramaters were incorrect to begin with but that was not what you asked
glad I could help wants exactly sure what you were trying to do.
Thanks Zoltan and Rodel,
That did help.
Rafel,
The weightage per activity is already given based on the resource requirement and its 7X7 job. So the duration consumed X by the weightage/ activity gives me the planned %.
Thanks
Jithin
And what about non-work days such as vacations?
And what about multiple resouces with different calendars?
And what about shiftwork on same activity?
Unless activities are duration type such as concrete curing status and updating is a matter of volume of work. Statusing and updating activities that perform volume of work without considering volume of work is not a good idea.
Zoltan furmula is correct with minor correction in case A > D or B < D or A=D.
=IF(B3<=$D$2,1,IF(A3<=$D$2,($D$2-A3+1)/(B3-A3+1),0))
Based on what you had here it is
=IF(B3=$D$2,1,IF(A3<$D$2,($D$2-A3+1)/(B3-A3+1)))