Percentage of Man-hours

A
ALALASUNDARAM RAVIKUMAR 👤 Member for 22 years 1 month

Hi

To have a rough guide, the % of cost and duration for the activities can be considered seperately. Then by comparing the 2 figures, you can decide what weightage to give for the activities. Any other suggestion from others?

Regards

Ravi

A
Anand Kulkarni 👤 Member for 21 years 2 months

Yes it’s really very fluid based completly on the project size and overall cost.



But individually package wise cost comes in picture later on only.



Yes architect’s comsumes maximum time but only thing is that maximum of time is overlap with construction.



I think dividing all the packages in 4 stages with typical sequence & obvious overlaps will be better.



Thing is what are details required from which agency & at what stage, which will kick-off working for the other agencies & susequently the other stage of the plan holds the key.



1) Concept drawings: 15-25 % (Project)



2) Detail Engineering drawings: 25-60% (Packages)



3) G.F.C. drawings: 50%-80% (Packages)



4) Shop floor drawings: 80%-100%


J
Jaco Stadler 👤 Member for 21 years 9 months

For industrial project it depends what your are building they are alway’s different.



o Structural - 10 % to 90 %

o Mechanical (HVAC & Plumbing) - 10 % to 90 %

o Electrical 10 % to 90 %

o Communication 10 % to 90 %

o Civil (Landscaping, Irrigation, Sewer and Drainage system) 10 % to 90 %

o Management (Project Management, Scheduling & Support)

4 % to 24 %


W
Waseem Saber 👤 Member for 21 years 7 months

hi imam,



this can be based on the two factors 1st the cost of all the indivdual disciplne summed and get the weighted factor for all the discipline on the overall-100% and other way is to summed all the design elements of the project and allocate/ the time neccessary to produced the outcome,the time required to produced the architecture dwgs may vary from that of the structure design, as it is directly link to the amount of the complexity of the project and the detailing required, unless you define these factors it is difficult to assess the situation and allocate the weighted factors.



calling the PPers on the same wave length to respond and share their experiences Pl[.....]ase.



cheers!

waseem saber

Forum Sponsor

Top Posters

Erkan Polater
9 posts
Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts