Hello everyone, I am facing a problem in resource leveling. After completion the scheduling, I faced with overallocation. As a result, i defined priority and used leveling, but unfortunately no change is happened. anybody has idea what could be the reason? Thanks
Resource Leveling
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Rodel,
Rodel,
Hamid,
Make sure that no overallocated on each activities as it will not move because it is already overallocated. Overlaping activities is fine as long as it will be level accordingly. Make sure the maximum limit is set ex: say 5 res x 8hrs/day = 40hrs/day
Hi Hamid,
As you mentioned, your setting is Fixed Units. Is the activity itself is over allocated? It so then overallocated resource on activities will not move or will not level.
Hi Rodel,
I selected “Preserve scheduled early and late dates” and some change has happened, but still, I am faced with over-allocated resources in some parts.
Hi Rodel,
I selected “Preserve scheduled early and late dates” and some change has happened, but still, I am faced with over-allocated resources in some parts.
Hi Hamid,
When you run Level Resource (shift+F9). Did you select:
1. Automatically Level Resources when scheduling
2. Preserve schedule early and late dates
3. Level all resources
Also did you select the field names you use for levelling priorities?